Operations manager during the final construction phase, commissioning and start up of the pulverised coal injection plant as part of a 15-year service agreement with BHP Steel Steelworks at Port Kembla NSW (Total capital $100M).
- Prepared operator/maintainers for commissioning and start up including 3 weeks of training overseas;
- Negotiated and sign off enterprise bargaining agreement (EBA) with 3 major unions (AMWU, ETU & AWU);
- Carried out HAZOPS, CHAZOPs and detailed risk assessment of a hazardous gas plant – developed safe system of work;
- Achieved 13 years no Lost Time Injuries (LTI’s)
- Successful start up and achieved maximum injection rates in 40 days (25 days ahead of schedule).